We issue costs orders to companies after AER hearings. Cost orders require companies to pay for some of the expenses incurred by participants to take part in a hearing. Hearing participants may apply for a cost order by submitting their cost claims to the AER.
A participant can be a person, group, or association of persons who have been permitted to participate in a hearing.
Order Number | Company Name | Application Number | Description | Date Sort ascending |
---|---|---|---|---|
ECO 2009-005 | Bearspaw Petroleum Ltd. | 1451117, 1457452, 1462817, 1462821, and 1509981 | Application for Two Wells and Two Pipeline Licences - Crossfield Field | |
ECO 2009-004 | Highpine Oil & Gas Limited | 1520574, 1521704,1521626, and 1525497 | Applications for Three Well Licences - Pembina Field, Tomahawk Area | |
ECO 2009-003 | Shell Canada Limited | 1498479, 1483571, 1520938, and 1520937 | Applications for Well, Pipeline, and Associated Facility Licences - Waterton Field | |
ECO 2009-002 | OMERS Energy Inc. | 1519973 | Application for a Pipeline Licence - Royal Field | |
ECO 2009-001 | Canadian Natural Resources Ltd. | 1518483, 1525506, 1525527, and 1525629 | Application for a Well Licence, a Facility Licence, and Two Pipeline Licences - Bentley Field | |
ECO 2008-016 | Standard Energy Inc. | Cost Application No. 1586737, Application No. 1543589 | Application for a Multiwell Licence Grande Prairie Field | |
ECO 2008-015 | Highpine Energy Ltd. | Cost Application No. 1582370, Applications No. 1525928, 1525932, 1526517, 1526582, 1526699, and 1526703 | Application for Six Well Licences Pembina Field | |
ECO 2008-014 | Quicksilver Resources Canada Inc. | Cost Application No. 1584590, Application No. 1554690 | Application for a Well Licence Amendment Honeysuckle Field | |
ECO 2008-013 | Standard Energy Inc. | Cost Application No. 1578554, Application No. 1517825 | Application for a Multiwell Licence Grande Prairie Field | |
ECO 2008-011 | West Energy Ltd. | Cost Application No. 1548553, Application No. 1545126 | Board-Initiated Review Hearing Regarding Decision 2007-061, Pembina Field |